Groundbreaking Ceremony of Dai Lai Eco-Residence and Resort Project, Ngoc Thanh Commune, Phuc Yen City, Vinh Phuc Province
On December 14, 2022, INVESTCORP CREATION Joint Stock Company attended the groundbreaking ceremony of Dai Lai Eco-Residence and Resort Project in Ngoc Thanh Commune, Phuc Yen City, Vinh Phuc Province held by the Main Contractor - Viet Hung Trading and Infrastructure Construction Joint Stock Company and the Investor - IFT Joint Stock Company.
Construction progress updated in November 2022 – Sao Mai Lam Son - Sao Vang New Urban Area Project, Xuan Thang Commune, Tho Xuan District, Thanh Hoa Province
Construction progress updated in November 2022 – Sao Mai Lam Son - Sao Vang New Urban Area Project, Xuan Thang Commune, Tho Xuan District, Thanh Hoa ProvinceaIn November 2022, INVESTCORP 6 continued to speed up the construction progress of the works in the contract including leveling the ground, pouring concrete, installing stone pavements, paving pavements to complete the water collection manholes and flower beds around. Total construction volume in November has reached about 15% of completed volume.
Construction progress updated in November 2022 – Project of Repairing damage to foundation, road surface, drainage system and traffic safety at section Km51+600 - Km53+500; Km57+00 - Km59+700, National way 47, Thanh Hoa province
In November 2022, INVESTCORP Land Thanh Hoa has focused on completing the excavation and installation of trench components of the drainage system. At the same time, INVESTCORP Land Thanh Hoa has also been implementing the construction of repairing the pavement with severe cracks, peeling, potholes. In addition, the work of repairing the rubber surface, subsidence, and watering the adhesive resin, asphalt concrete mats have also been completed by INVESTCORP Land Thanh Hoa. Total construction volume is estimated at 91% of contract volume.
Construction progress updated in November 2022 – Expansion project of Meiko Quang Minh manufacturing and assembling electronic components factory - Phase 1
In November 2022, INVESTCORP Dong Minh continued to carry out the works in the PCB area, including construction of the floor, construction of walls, stairs, plastering, tiling, and erection of steel doors. For the Underground Water Tank – Parking house, INVESTCORP Dong Minh has completed the wall construction and plastering. At the same time, INVESTCORP Dong Minh is also implementing the paving stairs, painting walls, railings, etc.
Groundbreaking ceremony of renovation and upgrade project of rescue road in Truong Xuan commune to left dike of Chu river, Tho Xuan district, Thanh Hoa province
On November 19, 2022, INVESTCORP Land Thanh Hoa Company Limited held a groundbreaking ceremony of the renovation and upgrade project of rescue road in Truong Xuan commune to the left dike of Chu river, Tho Xuan district, Thanh Hoa province. Attending the ceremony were representatives of the leaders of the project management board of Tho Xuan district, the Truong Xuan commune People's Committee, the Board of Directors and the construction team leaders of INVESTCORP Land Thanh Hoa.
Construction progress updated in November 2022 – Project of Technical infrastructure for residential area in Quang Dong commune, Thanh Hoa city, Thanh Hoa province
In November 2022, INVESTCORP Land Thanh Hoa Company Limited has focused on construction of project items under the contract. Construction works in the month includes dredging, road foundation excavation, K95 embankment achieved 100%; K98 embankment work achieved 95%. For the drainage system, the installation of the D600 sewer system has reached 81% and the sewer D400 has reached 24% of the contract volume.
Construction progress update in November 2022 – Typical Residential Area Infrastructure Project in Hoang Hoc Village, Dong Hoang Commune, Dong Son District, Thanh Hoa Province
In November 2022, INVESTCORP Land Thanh Hoa has implemented the construction of crushed stone type II and construction of crushed stone type I with over 90% of the volume.
Construction progress update in November 2022 – Road project from Xuan Hung commune connecting with road from Tho Xuan town to Lam Son – Sao Vang urban area, Tho Xuan district
In November 2022, INVESTCORP Land Thanh Hoa Company Limited continued to organize the construction of the items under the contract. The works performed in the month include traffic items and sewers.
Construction progress updated in November 2022 – Sakata Inx Vietnam Factory Project - Bac Ninh Branch
In November 2022, INVESTCORP 15 has completed the foundation work of the main factory, the concrete work of the factory floor has also been completed 75%, the wall building and plastering works are also being urgently constructed.
Construction progress updated in November 2022 – Sao Mai Resort Project, Tho Lam Commune - Tho Xuan District - Thanh Hoa Province
In November 2022, INVESTCORP 6 Company continued to implement the construction of items such as reception area, four-season villas, Bungalows on the lake and other ancillary items.
Construction progress updated in October 2022 – Project of Repairing damage to foundation, road surface, drainage system and traffic safety at section Km51+600 - Km53+500; Km57+00 - Km59+700, National way 47, Thanh Hoa province
In October 2022, INVESTCORP Land Thanh Hoa Company Limited has focused on speeding up the construction progress of the items in the contract. Items are under construction including drainage system, repairing damaged pavement, and traffic safety.
Construction progress updated in October 2022 – Project of Technical infrastructure for residential area in Quang Dong commune, Thanh Hoa city, Thanh Hoa province
In October 2022, INVESTCORP Land Thanh Hoa Company Limited has focused on constructing road surface and drainage system.
Construction progress update in October 2022 – Typical Residential Area Infrastructure Project in Hoang Hoc Village, Dong Hoang Commune, Dong Son District, Thanh Hoa Province
In October, 2022, INVESTCORP Land Thanh Hoa has carried out the construction of crushed stone for the subgrade II layer, reached 80% of the volume, construction and installation of curbs reached 98% and pavement paving reached 81%. At the same time, INVESTCORP Land Thanh Hoa has implemented to plant 98% of the tree volume.
Construction progress update in October 2022 – Road project from Xuan Hung commune connecting with road from Tho Xuan town to Lam Son – Sao Vang urban area, Tho Xuan district
At the end of October 2022, INVESTCORP Land Thanh Hoa has implemented and completed the repair and compaction of K98 grade I layer; completed the construction of the cut-off wall and the embankment of the stone roof reached 95%. In addition, transportation of weathered soil to the landfill is being implemented.
Construction progress updated in October 2022 – Sao Mai Lam Son - Sao Vang New Urban Area Project, Xuan Thang Commune, Tho Xuan District, Thanh Hoa Province
Sao Mai New Urban Area Project is invested by Sao Mai Group and the main contractor Vistar Joint Stock Company with a construction area of 704,354 m2. INVESTCORP Group has signed a contract to execute the project's pavement paving package and INVESTCORP 6 will directly execute the package.