Construction progress updated in November 2022 – Expansion project of Meiko Quang Minh manufacturing and assembling electronic components factory - Phase 1
In November 2022, INVESTCORP Dong Minh continued to carry out the works in the PCB area, including construction of the floor, construction of walls, stairs, plastering, tiling, and erection of steel doors. For the Underground Water Tank – Parking house, INVESTCORP Dong Minh has completed the wall construction and plastering. At the same time, INVESTCORP Dong Minh is also implementing the paving stairs, painting walls, railings, etc.
In the area of Power House, Cooling House and Air Compressor, INVESTCORP Dong Minh has basically completed plastering work and is implementing waterproofing, pouring concrete against heat on the roof. In addition, INVESTCORP Dong Minh is also installing rainwater drainage system outside the house and constructing roads (road foundation, welded steel mesh, and road concrete).
It is expected that by the end of December 2022, INVESTCORP Dong Minh will complete the PCB house, Underground water tank, Parking house, Boiler house and other works as planned.


- INVESTCORP Group Commences Construction of Meiko Yen Quang Project
- Groundbreaking Ceremony for the Construction and Finishing of ACM Wastewater Treatment Plant
- INVESTCORP OFFICIALLY AWARDED THE BKY PROJECT
- INVESTCORP ANNOUNCES NATIONAL DAY HOLIDAY SCHEDULE – 02 SEPTEMBER 2026
- Groundbreaking Ceremony for Meiko Electronics Hai Duong Vietnam Factory and Warehouse Project
- Announcement of Holiday schedule for Hung Kings’ Commemoration Day and April 30 & May 1, 2026
- Seminar Celebrating International Women’s Day
- INVESTCORP Group’s Early Spring Pilgrimage for Good Fortune at Am Tien Temple – Nua Mountain, Thanh Hoa