Construction progress update in October 2022 – Road project from Xuan Hung commune connecting with road from Tho Xuan town to Lam Son – Sao Vang urban area, Tho Xuan district
At the end of October 2022, INVESTCORP Land Thanh Hoa has implemented and completed the repair and compaction of K98 grade I layer; completed the construction of the cut-off wall and the embankment of the stone roof reached 95%. In addition, transportation of weathered soil to the landfill is being implemented.
As planned in November 2022, INVETSCORP Land Thanh Hoa will focus on executing road-related works, completing K98 embankment work, freestone embankment work, and construction of below crushed stone foundation.

Other news
- INVESTCORP Group Commences Construction of Meiko Yen Quang Project
- Groundbreaking Ceremony for the Construction and Finishing of ACM Wastewater Treatment Plant
- INVESTCORP OFFICIALLY AWARDED THE BKY PROJECT
- INVESTCORP ANNOUNCES NATIONAL DAY HOLIDAY SCHEDULE – 02 SEPTEMBER 2026
- Groundbreaking Ceremony for Meiko Electronics Hai Duong Vietnam Factory and Warehouse Project
- Announcement of Holiday schedule for Hung Kings’ Commemoration Day and April 30 & May 1, 2026
- Seminar Celebrating International Women’s Day
- INVESTCORP Group’s Early Spring Pilgrimage for Good Fortune at Am Tien Temple – Nua Mountain, Thanh Hoa
COPYRIGHT © 2021 INVESTCORP. ALL RIGHT RESERVED