Construction progress updated in October 2022 – Project of Technical infrastructure for residential area in Quang Dong commune, Thanh Hoa city, Thanh Hoa province
In October 2022, INVESTCORP Land Thanh Hoa Company Limited has focused on constructing road surface and drainage system.
For the road surface, INVETSCORP Land Thanh Hoa has carried out the construction of K98 road leveling, dredging, road foundation excavation, K95 embankment which have achieved 94%; processing and casting concrete components of the drainage system have reached 97%.
It is expected that in November 2022, INVESTCORP Land Thanh Hoa will focus on completing the construction and embankment of K95 and K98 road foundation, implementing the construction of grade II crushed stone base course of the roads that have been handed over the site; completing pavement embankment and rainwater drainage system for the remaining roads and fabricating and pouring components.

- INVESTCORP Group Commences Construction of Meiko Yen Quang Project
- Groundbreaking Ceremony for the Construction and Finishing of ACM Wastewater Treatment Plant
- INVESTCORP OFFICIALLY AWARDED THE BKY PROJECT
- INVESTCORP ANNOUNCES NATIONAL DAY HOLIDAY SCHEDULE – 02 SEPTEMBER 2026
- Groundbreaking Ceremony for Meiko Electronics Hai Duong Vietnam Factory and Warehouse Project
- Announcement of Holiday schedule for Hung Kings’ Commemoration Day and April 30 & May 1, 2026
- Seminar Celebrating International Women’s Day
- INVESTCORP Group’s Early Spring Pilgrimage for Good Fortune at Am Tien Temple – Nua Mountain, Thanh Hoa