Update construction progress – Lakeside Service Apartment (Myanmar) project in November 2020
At the end of November 2020, INVESTCORP Myanmar has completed all the installation of the piling-proof system and 95% of the excavation work at the Lakeside Myanmar Hotel project. At present, INVESTCORP Myanmar is continuing to implement underground works and urgently speeding up reinforced concrete structures including cutting bored piles, casting foundation lean concrete, fabricating and installing reinforced concrete and underground formwork. It is expected that the concrete work of underground structures will be started from December 1, 2020.
In December 2020, INVESTCORP Myanmar will try to complete the entire volume of foundation concrete, 50% of the basement area and speed up the construction of the basement walls. Waterproofing and soil filling work are also executed in late December 2020. The preparation of documents, drawings and materials for the structure and finishing is always prioritized to implement and order according to the project construction progress.


- Seminar Celebrating International Women’s Day
- INVESTCORP Group’s Early Spring Pilgrimage for Good Fortune at Am Tien Temple – Nua Mountain, Thanh Hoa
- INVESTCORP Group Holds Spring Opening Ceremony 2026
- INVESTCORP Group Announces the 2026 Lunar New Year Holiday Schedule
- 15th Anniversary of INVESTCORP Group 2025 Year-End Review - Happy New Year 2026
- Groundbreaking Ceremony of Yuanyou Vietnam Factory Project
- Groundbreaking Ceremony for Two Key Construction Projects of Thanh Hoa Provincial Police
- INVESTCORP Group Organizes Annual Employee Health Check-up Program 2025