Construction progress updated in November 2022 – Project of Repairing damage to foundation, road surface, drainage system and traffic safety at section Km51+600 - Km53+500; Km57+00 - Km59+700, National way 47, Thanh Hoa province
In November 2022, INVESTCORP Land Thanh Hoa has focused on completing the excavation and installation of trench components of the drainage system. At the same time, INVESTCORP Land Thanh Hoa has also been implementing the construction of repairing the pavement with severe cracks, peeling, potholes. In addition, the work of repairing the rubber surface, subsidence, and watering the adhesive resin, asphalt concrete mats have also been completed by INVESTCORP Land Thanh Hoa. Total construction volume is estimated at 91% of contract volume.
As planned in December 2022, INVESTCORP Land Thanh Hoa will continue to accelerate the construction progress, complete the works related to the concrete surface reinforcement, improve the traffic safety system and other infrastructure works to carry out the acceptance and handover of the project.


- Seminar Celebrating International Women’s Day
- INVESTCORP Group’s Early Spring Pilgrimage for Good Fortune at Am Tien Temple – Nua Mountain, Thanh Hoa
- INVESTCORP Group Holds Spring Opening Ceremony 2026
- INVESTCORP Group Announces the 2026 Lunar New Year Holiday Schedule
- 15th Anniversary of INVESTCORP Group 2025 Year-End Review - Happy New Year 2026
- Groundbreaking Ceremony of Yuanyou Vietnam Factory Project
- Groundbreaking Ceremony for Two Key Construction Projects of Thanh Hoa Provincial Police
- INVESTCORP Group Organizes Annual Employee Health Check-up Program 2025