Update construction progress – Yukioh factory project in September 2019
In September 2019, INVESTCORP Myanmar has completed some items of the factory, including the foundation system and bracing beams of the main workshop and office building. Currently, the internal roads, factory gates and areas connecting with the industrial zone are being implemented. The pit system and drainage ditches are also being carried out in parallel.
As planned in October 2019, INVESTCORP Myanmar will continue speeding up the construction of the floor of the main workshop and office building; continue constructing internal road system, drainage ditch system, pit system and some other items such as sewage tank, pump room, security house, inspection pit and factory fence...


Other news
- INVESTCORP Group Commences Construction of Meiko Yen Quang Project
- Groundbreaking Ceremony for the Construction and Finishing of ACM Wastewater Treatment Plant
- INVESTCORP OFFICIALLY AWARDED THE BKY PROJECT
- INVESTCORP ANNOUNCES NATIONAL DAY HOLIDAY SCHEDULE – 02 SEPTEMBER 2026
- Groundbreaking Ceremony for Meiko Electronics Hai Duong Vietnam Factory and Warehouse Project
- Announcement of Holiday schedule for Hung Kings’ Commemoration Day and April 30 & May 1, 2026
- Seminar Celebrating International Women’s Day
- INVESTCORP Group’s Early Spring Pilgrimage for Good Fortune at Am Tien Temple – Nua Mountain, Thanh Hoa
COPYRIGHT © 2021 INVESTCORP. ALL RIGHT RESERVED