Update construction progress – Technical Infrastructure Project of Dong Nam New Residential Area, Dong Khe Commune, Dong Son District, Thanh Hoa Province in September 2020
Dong Nam residential area infrastructure project in Dong Khe commune, Dong Son district, Thanh Hoa province, invested by the Management Board of construction and investment projects of Dong Son district having an area of nearly 10ha. Dong Nam residential area infrastructure project was commenced on July 3, 2020 by INVESTCORP Land Thanh Hoa Company Limited including traffic roads, water supply and drainage system, power supply system, green infrastructure and balancing reservoir.
At present, INVESTCORP Land Thanh Hoa has completed 282m of temporary road for construction, completing 80% of the excavation workload of organic mud for roads and 60% of transportation and embankment of K95 for roads no. 6, 7, 8, 9 and 12. Due to the rainy weather, some construction works were interrupted and could not be constructed continuously.
It is expected that in October 2020, INVESTCORP Land Thanh Hoa will complete the embankment of the K95 and K98 soil layers of the roads, prepare for the construction of surface drainage ditches, wastewater drainage and other related technique infrastructure.


- INVESTCORP Group Commences Construction of Meiko Yen Quang Project
- Groundbreaking Ceremony for the Construction and Finishing of ACM Wastewater Treatment Plant
- INVESTCORP OFFICIALLY AWARDED THE BKY PROJECT
- INVESTCORP ANNOUNCES NATIONAL DAY HOLIDAY SCHEDULE – 02 SEPTEMBER 2026
- Groundbreaking Ceremony for Meiko Electronics Hai Duong Vietnam Factory and Warehouse Project
- Announcement of Holiday schedule for Hung Kings’ Commemoration Day and April 30 & May 1, 2026
- Seminar Celebrating International Women’s Day
- INVESTCORP Group’s Early Spring Pilgrimage for Good Fortune at Am Tien Temple – Nua Mountain, Thanh Hoa