Update construction progress – Suga International (Vietnam) Factory project in October 2020
At the end of October 2020, INVESTCORP has completed all temporary works at Suga International (Vietnam) Factory project.
At the Factory & Office area, INVESTCORP has constructed 70% of the foundation workload, 50% of leveling and compacting work of the factory area. The garage, canteen and wastewater treatment tanks at auxiliary area have also reached 50% of the workload. The outdoor items is being constructed in parallel and 30% of the surrounding fence is completed.


Other news
- INVESTCORP Group Commences Construction of Meiko Yen Quang Project
- Groundbreaking Ceremony for the Construction and Finishing of ACM Wastewater Treatment Plant
- INVESTCORP OFFICIALLY AWARDED THE BKY PROJECT
- INVESTCORP ANNOUNCES NATIONAL DAY HOLIDAY SCHEDULE – 02 SEPTEMBER 2026
- Groundbreaking Ceremony for Meiko Electronics Hai Duong Vietnam Factory and Warehouse Project
- Announcement of Holiday schedule for Hung Kings’ Commemoration Day and April 30 & May 1, 2026
- Seminar Celebrating International Women’s Day
- INVESTCORP Group’s Early Spring Pilgrimage for Good Fortune at Am Tien Temple – Nua Mountain, Thanh Hoa
COPYRIGHT © 2021 INVESTCORP. ALL RIGHT RESERVED