Update construction progress – Suga International (Vietnam) Factory project in March 2021
In March 2021, at the Main factory and the Office building of the Suga International (Vietnam) factory project, INVESTCORP has completed the installation of panel walls inside and outside the factory area; completed the entire plastering work, 90% of the painting, gypsum ceiling, and 80% of the tiling. At present, INVESTCORP is continuing to construct internal finishing items such as ground epoxy, elevator installation, construction of aluminum and glass doors, iron doors, rolling doors and fire protection system.
At the Parking house and Canteen area, INVESTCORP has completed the plastering and brick works and 80% of the paint volume. The tiling work and fire protection system are also continuing to be carried out.
At the outdoor and auxiliary area, INVESTCORP has completed the construction of the outdoor concrete road, 70% of the asphalt road and continued to proceed skim coat and painting, fence and curb installation.



- INVESTCORP Group Commences Construction of Meiko Yen Quang Project
- Groundbreaking Ceremony for the Construction and Finishing of ACM Wastewater Treatment Plant
- INVESTCORP OFFICIALLY AWARDED THE BKY PROJECT
- INVESTCORP ANNOUNCES NATIONAL DAY HOLIDAY SCHEDULE – 02 SEPTEMBER 2026
- Groundbreaking Ceremony for Meiko Electronics Hai Duong Vietnam Factory and Warehouse Project
- Announcement of Holiday schedule for Hung Kings’ Commemoration Day and April 30 & May 1, 2026
- Seminar Celebrating International Women’s Day
- INVESTCORP Group’s Early Spring Pilgrimage for Good Fortune at Am Tien Temple – Nua Mountain, Thanh Hoa