Update construction progress – Suga International (Vietnam) Factory project in February 2021
At the end of February 2021, INVESTCORP has completed the corrugated iron roof of the factory, completed the erection of the exterior panel walls and 90% of the plastering of the Factory and Office of Suga International Factory (Vietnam) project. At present, INVESTCORP is continuing to construct indoor finishing items such as gypsum ceilings and walls, panel ceilings and walls, foundation paint, paintwork and fire protection system.
In the Parking and Canteen area, INVESTCORP has completed the structural items and continues to implement finishing works such as plastering, tiling and painting.
For the outdoor and auxiliary items, INVESTCORP has completed the construction of the water tank system, the wastewater treatment tank while continuing to construct the outdoor drainage and the internal road system. The main gate, secondary gate and guardhouse are also continuing to be implemented.


- INVESTCORP Group Commences Construction of Meiko Yen Quang Project
- Groundbreaking Ceremony for the Construction and Finishing of ACM Wastewater Treatment Plant
- INVESTCORP OFFICIALLY AWARDED THE BKY PROJECT
- INVESTCORP ANNOUNCES NATIONAL DAY HOLIDAY SCHEDULE – 02 SEPTEMBER 2026
- Groundbreaking Ceremony for Meiko Electronics Hai Duong Vietnam Factory and Warehouse Project
- Announcement of Holiday schedule for Hung Kings’ Commemoration Day and April 30 & May 1, 2026
- Seminar Celebrating International Women’s Day
- INVESTCORP Group’s Early Spring Pilgrimage for Good Fortune at Am Tien Temple – Nua Mountain, Thanh Hoa