Update construction progress – Sankyo project in June 2019
At the end of June 2019, INVESTCORP Myanmar received the office area from the Owner to implement finishing works and is expected to receive the workshop area in July 2019.
Auxiliary items such as pump room, INVESTCORP Myanmar is carrying out underground water tanks, columns and floors as well as preparing to build pump room’s walls. The security guard has finished brickwork and is under construction. The power room’s foundation is under construction.
At the outdoor area, INVESTCORP Myanmar has completed the construction of drainage ditches, is continuing to execute access road, fence and processing gate.



Other news
- INVESTCORP Group Commences Construction of Meiko Yen Quang Project
- Groundbreaking Ceremony for the Construction and Finishing of ACM Wastewater Treatment Plant
- INVESTCORP OFFICIALLY AWARDED THE BKY PROJECT
- INVESTCORP ANNOUNCES NATIONAL DAY HOLIDAY SCHEDULE – 02 SEPTEMBER 2026
- Groundbreaking Ceremony for Meiko Electronics Hai Duong Vietnam Factory and Warehouse Project
- Announcement of Holiday schedule for Hung Kings’ Commemoration Day and April 30 & May 1, 2026
- Seminar Celebrating International Women’s Day
- INVESTCORP Group’s Early Spring Pilgrimage for Good Fortune at Am Tien Temple – Nua Mountain, Thanh Hoa
COPYRIGHT © 2021 INVESTCORP. ALL RIGHT RESERVED