Update construction progress – Sankyo project in July 2019
In July 2019, INVESTCORP Myanmar speeded up the implementation of all items of the project. At the outdoor area, concrete road and drainage ditches have been basically completed. For the factory, INVESTCORP Myanmar has completed concrete work, plastering work and is carrying out finishing work.
The guard house, power room and pump room have been done. Some other items such as gate, fence, foundation pit and tank system are being executed. Finishing works of the office area and concrete yard have also been completed.
Currently, the project is still being implemented by INVESTCORP Myanmar on schedule and will be handed over to the Owner in September 2019.

Other news
- INVESTCORP Group Commences Construction of Meiko Yen Quang Project
- Groundbreaking Ceremony for the Construction and Finishing of ACM Wastewater Treatment Plant
- INVESTCORP OFFICIALLY AWARDED THE BKY PROJECT
- INVESTCORP ANNOUNCES NATIONAL DAY HOLIDAY SCHEDULE – 02 SEPTEMBER 2026
- Groundbreaking Ceremony for Meiko Electronics Hai Duong Vietnam Factory and Warehouse Project
- Announcement of Holiday schedule for Hung Kings’ Commemoration Day and April 30 & May 1, 2026
- Seminar Celebrating International Women’s Day
- INVESTCORP Group’s Early Spring Pilgrimage for Good Fortune at Am Tien Temple – Nua Mountain, Thanh Hoa
COPYRIGHT © 2021 INVESTCORP. ALL RIGHT RESERVED