Update construction progress of Wearing apparels manufacturing project - Ramatex Hai Phong in Nov 2018
By the end of Nov 2018, at Block 1 of the Wearing apparels manufacturing project - Ramatex Hai Phong, INVESTCORP is carrying out some arising works as requested by the Owner.
At Block 2 of the project, the whole construction work of the Production building No. 3&4 and the Office No. 2 are basically completed. At present, INVESTCORP is proceeding finishing work such as Epoxy for ground; touching and external repair; repair of drainage system and asphalt surface treatment.
The auxiliary items such as parking house is roofed with corrugated iron and installed accessories. The drainage system and sub gate are completed. The internal road is being carried out the road level and curb installation. Fence is being painted and will be completed on Dec 5, 2018.
It is expected that the whole project will be accepted and handed over to the Owner in Dec 2018.





- INVESTCORP Group Commences Construction of Meiko Yen Quang Project
- Groundbreaking Ceremony for the Construction and Finishing of ACM Wastewater Treatment Plant
- INVESTCORP OFFICIALLY AWARDED THE BKY PROJECT
- INVESTCORP ANNOUNCES NATIONAL DAY HOLIDAY SCHEDULE – 02 SEPTEMBER 2026
- Groundbreaking Ceremony for Meiko Electronics Hai Duong Vietnam Factory and Warehouse Project
- Announcement of Holiday schedule for Hung Kings’ Commemoration Day and April 30 & May 1, 2026
- Seminar Celebrating International Women’s Day
- INVESTCORP Group’s Early Spring Pilgrimage for Good Fortune at Am Tien Temple – Nua Mountain, Thanh Hoa