Update construction progress of Vietnam Mie factory project phase 2 in Feb 2019
In Feb 2019, INVESTCORP finished 50% of the foundation framework, beam and bracing at the workshop of the Vietnam Mie factory project phase 2. All construction stages are inspected by the Owner before moving to next steps.
Auxiliary items such as signal boards and internal rules have been finished. Piling work for construction of the water tank is started implementing.
It is expected that in Mar 2019, the foundation items, water tank, brickwork and drainage system will be started implementing.



Other news
- INVESTCORP Group Commences Construction of Meiko Yen Quang Project
- Groundbreaking Ceremony for the Construction and Finishing of ACM Wastewater Treatment Plant
- INVESTCORP OFFICIALLY AWARDED THE BKY PROJECT
- INVESTCORP ANNOUNCES NATIONAL DAY HOLIDAY SCHEDULE – 02 SEPTEMBER 2026
- Groundbreaking Ceremony for Meiko Electronics Hai Duong Vietnam Factory and Warehouse Project
- Announcement of Holiday schedule for Hung Kings’ Commemoration Day and April 30 & May 1, 2026
- Seminar Celebrating International Women’s Day
- INVESTCORP Group’s Early Spring Pilgrimage for Good Fortune at Am Tien Temple – Nua Mountain, Thanh Hoa
COPYRIGHT © 2021 INVESTCORP. ALL RIGHT RESERVED