Update construction progress of Textile dyeing and garment factory project – Ramatex Nam Dinh phase 2 in November 2020
In November 2020, at the main Factory area, INVESTCORP completed the entire construction of the structure. It is expected that the plastering work will be completed on December 10, 2020, finishing works such as toilet and stair tiling, painting, gypsum ceilings and walls, doors, windows, glass walls... will also be completed in December 2020.
In the Kitchen and Canteen area, INVESTCORP has completed the plastering and roofing; finishing items will be carried out after being approved by the Investor.
The Warehouse has been completed 95% of the corrugated iron, 60% of the paint volume and started to put on the roof’s flashing. It is expected that INVESTCCORP will hand over the Warehouse to the Investor on December 31, 2020.
The Rubbish house area is being primed and will be put on the finishing paint before handover. The pump room and control room have completed roofing, interior painting and exterior priming. The construction of the Garage is waiting for approval from the Investor.
Regarding the outdoor items, the trench system has been constructed reaching 90% of the volume and the concrete road will continue to be constructed to complete in December 2020 as scheduled.


- INVESTCORP Group Commences Construction of Meiko Yen Quang Project
- Groundbreaking Ceremony for the Construction and Finishing of ACM Wastewater Treatment Plant
- INVESTCORP OFFICIALLY AWARDED THE BKY PROJECT
- INVESTCORP ANNOUNCES NATIONAL DAY HOLIDAY SCHEDULE – 02 SEPTEMBER 2026
- Groundbreaking Ceremony for Meiko Electronics Hai Duong Vietnam Factory and Warehouse Project
- Announcement of Holiday schedule for Hung Kings’ Commemoration Day and April 30 & May 1, 2026
- Seminar Celebrating International Women’s Day
- INVESTCORP Group’s Early Spring Pilgrimage for Good Fortune at Am Tien Temple – Nua Mountain, Thanh Hoa