Update construction progress of Tamada Office and Warehouse project in Mar 2019
In Mar 2019, at the office area, INVESTCORP Myanmar completed beam and slab items of the 1st floor and assembly of roof and surrounding iron fence. Plastering work at the office is being carried out. As expected in Apr 2019, INVESTCORP Myanmar will proceed casting ground slab concrete.
At the warehouse, slab and beam and assembly of steel structure were completed. At present, 50% of assembly work of roof and surrounding fence are being done.
Ancillary items such as guardhouse, pump room, concrete road and gate will be proceeded in Apr 2019. Drainage system, fence and water tanks are being implemented.

Other news
- INVESTCORP Group Commences Construction of Meiko Yen Quang Project
- Groundbreaking Ceremony for the Construction and Finishing of ACM Wastewater Treatment Plant
- INVESTCORP OFFICIALLY AWARDED THE BKY PROJECT
- INVESTCORP ANNOUNCES NATIONAL DAY HOLIDAY SCHEDULE – 02 SEPTEMBER 2026
- Groundbreaking Ceremony for Meiko Electronics Hai Duong Vietnam Factory and Warehouse Project
- Announcement of Holiday schedule for Hung Kings’ Commemoration Day and April 30 & May 1, 2026
- Seminar Celebrating International Women’s Day
- INVESTCORP Group’s Early Spring Pilgrimage for Good Fortune at Am Tien Temple – Nua Mountain, Thanh Hoa
COPYRIGHT © 2021 INVESTCORP. ALL RIGHT RESERVED