Update construction progress of New pressing factory project of Mitsuba M-Tech Vietnam Co. Ltd in Sep 2018
By the end of Sep 2018, at the New pressing factory project of Mitsuba M-Tech Vietnam Co. Ltd, all brickwork and ground croncrete has been finished. At present, INVESTCORP is carrying out plastering work and has finished to 90%. As expectation, the plastering work will have been finished by Oct 15, 2018.
Finish works such as painting, ceiling, gypsum walls and window processing etc. are also implemented in parallel. Rainwater drainage system is also completed by INVESTCORP. Installaion of pavement curb and outdoor road system is under construction.
It is expected by then end of Oct 2018, INVESTCORP will basically finish the whole project for acceptance and handover in Nov 2018.


Other news
- INVESTCORP Group Commences Construction of Meiko Yen Quang Project
- Groundbreaking Ceremony for the Construction and Finishing of ACM Wastewater Treatment Plant
- INVESTCORP OFFICIALLY AWARDED THE BKY PROJECT
- INVESTCORP ANNOUNCES NATIONAL DAY HOLIDAY SCHEDULE – 02 SEPTEMBER 2026
- Groundbreaking Ceremony for Meiko Electronics Hai Duong Vietnam Factory and Warehouse Project
- Announcement of Holiday schedule for Hung Kings’ Commemoration Day and April 30 & May 1, 2026
- Seminar Celebrating International Women’s Day
- INVESTCORP Group’s Early Spring Pilgrimage for Good Fortune at Am Tien Temple – Nua Mountain, Thanh Hoa
COPYRIGHT © 2021 INVESTCORP. ALL RIGHT RESERVED