Update construction progress of Myanmar Meranti project’s Ruby in Sep 2018
In Sep 2018, at the Myanmar Meranti project’s Ruby, 60% of the production building’s ground area has been done by INVESTCORP Myanmar. The remaining area will be continued to implement after the foundation for machines is completed.
At the moment, INVESTCORP Myanmar is constructing the enclosing wall around the factory and cable trough for the power room.
It is expected in Oct 2018, construction of foundation for machines inside the production building and some auxiliary items will be carried out by INVESTCORP Myanmar.


Other news
- INVESTCORP Group Commences Construction of Meiko Yen Quang Project
- Groundbreaking Ceremony for the Construction and Finishing of ACM Wastewater Treatment Plant
- INVESTCORP OFFICIALLY AWARDED THE BKY PROJECT
- INVESTCORP ANNOUNCES NATIONAL DAY HOLIDAY SCHEDULE – 02 SEPTEMBER 2026
- Groundbreaking Ceremony for Meiko Electronics Hai Duong Vietnam Factory and Warehouse Project
- Announcement of Holiday schedule for Hung Kings’ Commemoration Day and April 30 & May 1, 2026
- Seminar Celebrating International Women’s Day
- INVESTCORP Group’s Early Spring Pilgrimage for Good Fortune at Am Tien Temple – Nua Mountain, Thanh Hoa
COPYRIGHT © 2021 INVESTCORP. ALL RIGHT RESERVED