Update construction progress of Myanmar Meranti project’s Ruby in Nov 2018
At present, at the Myanmar Meranti project’s Ruby of Merantee Ltd., INVESTCORP Myanmar is proceeding structure construction of some auxiliary houses and internal cable troughs of the auxiliary houses.
For the additional machine foundation inside the workshop, INVESTCORP Myanmar is constructing reinforcement work, formwork for foundation base and continues excavation work of the next machine foundations. As expectation, the excavation work will be completed in Dec 2018.
At the main workshop area, related items such as ground concrete, brickwork and finishing work will be implemented in the coming time.



Other news
- INVESTCORP Group Commences Construction of Meiko Yen Quang Project
- Groundbreaking Ceremony for the Construction and Finishing of ACM Wastewater Treatment Plant
- INVESTCORP OFFICIALLY AWARDED THE BKY PROJECT
- INVESTCORP ANNOUNCES NATIONAL DAY HOLIDAY SCHEDULE – 02 SEPTEMBER 2026
- Groundbreaking Ceremony for Meiko Electronics Hai Duong Vietnam Factory and Warehouse Project
- Announcement of Holiday schedule for Hung Kings’ Commemoration Day and April 30 & May 1, 2026
- Seminar Celebrating International Women’s Day
- INVESTCORP Group’s Early Spring Pilgrimage for Good Fortune at Am Tien Temple – Nua Mountain, Thanh Hoa
COPYRIGHT © 2021 INVESTCORP. ALL RIGHT RESERVED