Update construction progress of Myanmar Meranti project’s Ruby in May 2019
In May 2019, INVESTCORP Myanmar continued to execute the painting and finishing works of the ancillary area. Other finishing works are also implemented in parallel.
The additional PIT foundation inside the factory has been completed and handed over to the Owner for use. At present, INVESTCORP Myanmar is doing cleaning work and gluing expansion joints.
At the main workshop area, INVESTCORP Myanmar is carrying out the painting work and completing 90% of the workload. Finishing work of the toilet area is continuing to be executed and be expected to complete on June 15, 2019. Besides, some other finishing works are also being implemented.



Other news
- INVESTCORP Group Commences Construction of Meiko Yen Quang Project
- Groundbreaking Ceremony for the Construction and Finishing of ACM Wastewater Treatment Plant
- INVESTCORP OFFICIALLY AWARDED THE BKY PROJECT
- INVESTCORP ANNOUNCES NATIONAL DAY HOLIDAY SCHEDULE – 02 SEPTEMBER 2026
- Groundbreaking Ceremony for Meiko Electronics Hai Duong Vietnam Factory and Warehouse Project
- Announcement of Holiday schedule for Hung Kings’ Commemoration Day and April 30 & May 1, 2026
- Seminar Celebrating International Women’s Day
- INVESTCORP Group’s Early Spring Pilgrimage for Good Fortune at Am Tien Temple – Nua Mountain, Thanh Hoa
COPYRIGHT © 2021 INVESTCORP. ALL RIGHT RESERVED