Update construction progress of Myanmar Meranti project’s Ruby in June 2018
By the end of June 2018, the whole foundation and bracing beam of the factory of the Myanmar Meranti project’s Ruby have been completed by INVESTCORP Myanmar.
At present, the foundation and floor levelling of the factory are being carried out by INVESTCORP Myanmar. It is expected that in July 2018, concrete work for the factory floor will be proceeded.


Other news
- INVESTCORP Group Commences Construction of Meiko Yen Quang Project
- Groundbreaking Ceremony for the Construction and Finishing of ACM Wastewater Treatment Plant
- INVESTCORP OFFICIALLY AWARDED THE BKY PROJECT
- INVESTCORP ANNOUNCES NATIONAL DAY HOLIDAY SCHEDULE – 02 SEPTEMBER 2026
- Groundbreaking Ceremony for Meiko Electronics Hai Duong Vietnam Factory and Warehouse Project
- Announcement of Holiday schedule for Hung Kings’ Commemoration Day and April 30 & May 1, 2026
- Seminar Celebrating International Women’s Day
- INVESTCORP Group’s Early Spring Pilgrimage for Good Fortune at Am Tien Temple – Nua Mountain, Thanh Hoa
COPYRIGHT © 2021 INVESTCORP. ALL RIGHT RESERVED