Update construction progress of Myanmar Meranti project’s Ruby in July 2018
By the end of July 2018, construction for the whole foundation of the main workshop of the Myanmar Meranti project’s Ruby has been completed by INVESTCORP Myanmar.
At present, ground levelling, foundation concrete and ground concrete are being constructed by INVESTCORP Myanmar. It is expected that in August 2018, 50% of the ground square of the workshop will be finished.
The auxiliary items such as pits inside the workshop, ancillary houses and waste water treatment tank will be carried out in the coming time.




Other news
- INVESTCORP Group Commences Construction of Meiko Yen Quang Project
- Groundbreaking Ceremony for the Construction and Finishing of ACM Wastewater Treatment Plant
- INVESTCORP OFFICIALLY AWARDED THE BKY PROJECT
- INVESTCORP ANNOUNCES NATIONAL DAY HOLIDAY SCHEDULE – 02 SEPTEMBER 2026
- Groundbreaking Ceremony for Meiko Electronics Hai Duong Vietnam Factory and Warehouse Project
- Announcement of Holiday schedule for Hung Kings’ Commemoration Day and April 30 & May 1, 2026
- Seminar Celebrating International Women’s Day
- INVESTCORP Group’s Early Spring Pilgrimage for Good Fortune at Am Tien Temple – Nua Mountain, Thanh Hoa
COPYRIGHT © 2021 INVESTCORP. ALL RIGHT RESERVED