Update construction progress of Myanmar Meranti project’s Ruby in Jan 2019
By the end of Jan 2019, at the Myanmar Meranti project’s Ruby of Meranti Ltd., INVESTCORP Myanmar is continuing to implement brickwork of some auxiliary houses and finish concrete surface of the cable trough. Painting work has started being implemented.
For the additional PIT in the workshop, at present, INVESTCORP Myanmar has cast 70% of the workload and is carried out the RC work and formwork of the foundation base and walls. Excavation and backfilling work of the remaining PIT is also implemented in parallel and is expected to be completed in Feb 2019.
At the main workshop, relating items such as casting concrete around PIT is completed according to each area. Painting and finishing works of the toilet areas are also finished 98% of the plastering work. Some of other finishing works will be carried out in the next time.





- INVESTCORP Group Commences Construction of Meiko Yen Quang Project
- Groundbreaking Ceremony for the Construction and Finishing of ACM Wastewater Treatment Plant
- INVESTCORP OFFICIALLY AWARDED THE BKY PROJECT
- INVESTCORP ANNOUNCES NATIONAL DAY HOLIDAY SCHEDULE – 02 SEPTEMBER 2026
- Groundbreaking Ceremony for Meiko Electronics Hai Duong Vietnam Factory and Warehouse Project
- Announcement of Holiday schedule for Hung Kings’ Commemoration Day and April 30 & May 1, 2026
- Seminar Celebrating International Women’s Day
- INVESTCORP Group’s Early Spring Pilgrimage for Good Fortune at Am Tien Temple – Nua Mountain, Thanh Hoa