Update construction progress of HTMP mold and plastic part manufacturing project in Nov 2018
By the end of Nov 2018, INVESTCORP has completed installation of steel structure, completed 90% of the workload of plastering work and moved to roof work of the office area at the HTMP mold and plastic part manufacturing project. Finishing works such as painting, ceiling and partition, tiling and glazing are started proceeding.
At the workshop area, 70% of concrete work has been finished. As expected, concrete structure of the 2nd floor will be completed by INVESTCORP on Dec 6, 2018. Besides, painting work of the 1st floor is also started carrying out.
At the auxiliary houses, at present, INVESTCORP has implemented structure work of the auxiliary houses No. 1,2&3. The auxiliary houses No. 4,5,6,7,8&9 will be started constructing in the 1st week of Dec 2018.
The outdoor items such as underground tank is being constructed by dropped down method. It is expected that the underground tank’s structure will be completed on Dec 10, 2018. Road work and manhole concrete are being implemented. Surrounding fence has been completed to 50% of the workload.
At present, all of the construction items are keeping up with the master progress of the project as requested by the Owner.



- INVESTCORP Group Commences Construction of Meiko Yen Quang Project
- Groundbreaking Ceremony for the Construction and Finishing of ACM Wastewater Treatment Plant
- INVESTCORP OFFICIALLY AWARDED THE BKY PROJECT
- INVESTCORP ANNOUNCES NATIONAL DAY HOLIDAY SCHEDULE – 02 SEPTEMBER 2026
- Groundbreaking Ceremony for Meiko Electronics Hai Duong Vietnam Factory and Warehouse Project
- Announcement of Holiday schedule for Hung Kings’ Commemoration Day and April 30 & May 1, 2026
- Seminar Celebrating International Women’s Day
- INVESTCORP Group’s Early Spring Pilgrimage for Good Fortune at Am Tien Temple – Nua Mountain, Thanh Hoa





