Update construction progress of HTMP mold and plastic part manufacturing project in Feb 2019
By the end of Feb 2019, after nearly 7 months of construction at the HTMP mold and plastic part manufacturing project, INVESTCORP has completed to 95% of the indoor items. At the moment, the final finishing works are carried out.
Outdoor items such as concrete road, drainage system, fence, gate and greenery work ect. will be completed by 15 Mar 2019.
The whole project will be inspected and handed over to the Owner to put into use on 20 Mar 2019.



Other news
- INVESTCORP Group Commences Construction of Meiko Yen Quang Project
- Groundbreaking Ceremony for the Construction and Finishing of ACM Wastewater Treatment Plant
- INVESTCORP OFFICIALLY AWARDED THE BKY PROJECT
- INVESTCORP ANNOUNCES NATIONAL DAY HOLIDAY SCHEDULE – 02 SEPTEMBER 2026
- Groundbreaking Ceremony for Meiko Electronics Hai Duong Vietnam Factory and Warehouse Project
- Announcement of Holiday schedule for Hung Kings’ Commemoration Day and April 30 & May 1, 2026
- Seminar Celebrating International Women’s Day
- INVESTCORP Group’s Early Spring Pilgrimage for Good Fortune at Am Tien Temple – Nua Mountain, Thanh Hoa
COPYRIGHT © 2021 INVESTCORP. ALL RIGHT RESERVED