Update construction progress of EMS extension project of Meiko Electronics Vietnam Company Ltd in Oct 2018
By the end of Oct 2018, after nearly 2 months of commencement of the EMS extension project of Meiko Electronics Vietnam Company, INVESTCORP has completed all temporary items for construction of the project such as temporary office and temporary fence; completed construction of the entire foundation work and the ground levelling.
At the moment, INVESTCORP is constructing in parallel the ground slab and the reinforced concrete structure of columns, beams and slabs of the 2nd floor.
As expectation, all of the reinforced concrete structure of the factory will be completed by INVESTCORP at the beginning of Dec 2018.




Other news
- INVESTCORP Group Commences Construction of Meiko Yen Quang Project
- Groundbreaking Ceremony for the Construction and Finishing of ACM Wastewater Treatment Plant
- INVESTCORP OFFICIALLY AWARDED THE BKY PROJECT
- INVESTCORP ANNOUNCES NATIONAL DAY HOLIDAY SCHEDULE – 02 SEPTEMBER 2026
- Groundbreaking Ceremony for Meiko Electronics Hai Duong Vietnam Factory and Warehouse Project
- Announcement of Holiday schedule for Hung Kings’ Commemoration Day and April 30 & May 1, 2026
- Seminar Celebrating International Women’s Day
- INVESTCORP Group’s Early Spring Pilgrimage for Good Fortune at Am Tien Temple – Nua Mountain, Thanh Hoa
COPYRIGHT © 2021 INVESTCORP. ALL RIGHT RESERVED