Update construction progress – Multifunctional house of Tho Xuan High school No 4, Tho Xuan district in February 2021
At the end of February 2021, INVESTCORP Land Thanh Hoa continued to construct the brickwork of the multifunctional house’s structure. The volume of the works done in the month includes fabrication and erection of formwork, reinforcement, concreting of curved roof beams cos + 9.80m and fabrication of steel structure at the factory.
As planned in March 2021, INVESTCORP Land Thanh Hoa will complete the construction of the remaining items, construction of plastering and painting works; transporting steel-frame structures to the project; installation of corrugated iron roofs, installation of drainage systems, tiling and constructing wooden floors.

Other news
- INVESTCORP Group Commences Construction of Meiko Yen Quang Project
- Groundbreaking Ceremony for the Construction and Finishing of ACM Wastewater Treatment Plant
- INVESTCORP OFFICIALLY AWARDED THE BKY PROJECT
- INVESTCORP ANNOUNCES NATIONAL DAY HOLIDAY SCHEDULE – 02 SEPTEMBER 2026
- Groundbreaking Ceremony for Meiko Electronics Hai Duong Vietnam Factory and Warehouse Project
- Announcement of Holiday schedule for Hung Kings’ Commemoration Day and April 30 & May 1, 2026
- Seminar Celebrating International Women’s Day
- INVESTCORP Group’s Early Spring Pilgrimage for Good Fortune at Am Tien Temple – Nua Mountain, Thanh Hoa
COPYRIGHT © 2021 INVESTCORP. ALL RIGHT RESERVED