Update construction progress – Meiko Quang Minh electronics assembling factory project in May 2020
By the end of May 2020, the items of the Main factory area have been completed by INVESTCORP including construction of the columns, slabs and beams, staircases of the second floor, third floor and roof floor. Construction of the columns, beams and attic floor reached 50% of the workload, brickwork and plastering work and staircases of the first floor reached 80%.
The underground water tanks have been completed piling work and excavation. At present, INVESTCORP is implementing the foundation construction.
Auxiliary items such as security house being completed 100% of the foundation work and brickwork. Fence foundation and fabrication of the fence steel frame are also completed. For the RMU, INVESTCORP has been completed excavation of the pit foundation, fabrication and installation of the reinforced concrete and formwork for casting concrete of the foundation.

- INVESTCORP Group Commences Construction of Meiko Yen Quang Project
- Groundbreaking Ceremony for the Construction and Finishing of ACM Wastewater Treatment Plant
- INVESTCORP OFFICIALLY AWARDED THE BKY PROJECT
- INVESTCORP ANNOUNCES NATIONAL DAY HOLIDAY SCHEDULE – 02 SEPTEMBER 2026
- Groundbreaking Ceremony for Meiko Electronics Hai Duong Vietnam Factory and Warehouse Project
- Announcement of Holiday schedule for Hung Kings’ Commemoration Day and April 30 & May 1, 2026
- Seminar Celebrating International Women’s Day
- INVESTCORP Group’s Early Spring Pilgrimage for Good Fortune at Am Tien Temple – Nua Mountain, Thanh Hoa





