Update construction progress – Meiko Quang Minh electronics assembling factory project in July 2020
In July 2020, INVESTCORP continued its efforts to carry out the Meiko Quang Minh electronics assembling factory project to hand over to the Investor on time.
In the Main factory, INVESTCORP has basically completed all plastering works, completed the construction of fire-rated doors and main doors etc. Currently, 90% of the aluminum glass windows and paintwork are also completed.
Underground water tank, pump room and ancillary items including guard house, gate, fence and RMU house have been completed. Roads, outdoor drainage systems and grass planting items were completed 100% by INVESTCORP.
Due to some changes, the project will be completed and handed over by INVESTCORP in August 2020.


Other news
- INVESTCORP Group Commences Construction of Meiko Yen Quang Project
- Groundbreaking Ceremony for the Construction and Finishing of ACM Wastewater Treatment Plant
- INVESTCORP OFFICIALLY AWARDED THE BKY PROJECT
- INVESTCORP ANNOUNCES NATIONAL DAY HOLIDAY SCHEDULE – 02 SEPTEMBER 2026
- Groundbreaking Ceremony for Meiko Electronics Hai Duong Vietnam Factory and Warehouse Project
- Announcement of Holiday schedule for Hung Kings’ Commemoration Day and April 30 & May 1, 2026
- Seminar Celebrating International Women’s Day
- INVESTCORP Group’s Early Spring Pilgrimage for Good Fortune at Am Tien Temple – Nua Mountain, Thanh Hoa
COPYRIGHT © 2021 INVESTCORP. ALL RIGHT RESERVED