Update construction progress in May 2021 – Dong Nam Residential area infrastructure project in Dong Khe commune, Dong Son district, Thanh Hoa province
In May 2021, INVESTCORP Land Thanh Hoa continued executing the work items in the contract. The volume of work done in the month includes: Completing pulling 60% of the underground cables and erecting lighting poles; 90% of the planting of trees on the roads; completing casting, constructing and installing curbs for roads No. 4, 5, 6, 7, 10, 11 & 12; completing construction of grade 2 crushed stone foundation for road No. 10, grade 1 crushed stone foundation for roads No. 4, 5, 6, 7, 11 & 12.
Implementation plan in June 2021: Constructing asphalt concrete for roads No. 4, 5, 6, 7, 10, 11 & 12; completing construction of water supply and drainage system; pulling low-voltage and medium-voltage cables, installing electrical cabinets, building the foundation of power station; completing the construction of crushed stone grade, installing the curbs on roads No. 8, 9, 13; planting trees, paving sidewalks in the infrastructure area.




- INVESTCORP Group Commences Construction of Meiko Yen Quang Project
- Groundbreaking Ceremony for the Construction and Finishing of ACM Wastewater Treatment Plant
- INVESTCORP OFFICIALLY AWARDED THE BKY PROJECT
- INVESTCORP ANNOUNCES NATIONAL DAY HOLIDAY SCHEDULE – 02 SEPTEMBER 2026
- Groundbreaking Ceremony for Meiko Electronics Hai Duong Vietnam Factory and Warehouse Project
- Announcement of Holiday schedule for Hung Kings’ Commemoration Day and April 30 & May 1, 2026
- Seminar Celebrating International Women’s Day
- INVESTCORP Group’s Early Spring Pilgrimage for Good Fortune at Am Tien Temple – Nua Mountain, Thanh Hoa