Update construction progress in May 2017 – Taiyo Nippon Sanso Myanmar Project.
In May 2017, it was rainy in Yangon, the works at the Taiyo Nippon Sanso project have been encountered many difficulties. However, with the determined spirit, the team of engineers and workers on the construction site has worked hard to ensure the expected schedule.
At the office area, formwork and rebar of slabs & beams on the 2nd floor have been accelerated to ensure the concrete pouring plan which is scheduled to start in early June 2017. The utility facilities such as the electric chambers, septic tanks, warehouses, etc. are being proceeding walls and foundations.
External work such as the drainage ditch system has reached 80% of total workload. In addition, the road work has completed the base & sub-base for embankment.






Other news
- INVESTCORP Group Commences Construction of Meiko Yen Quang Project
- Groundbreaking Ceremony for the Construction and Finishing of ACM Wastewater Treatment Plant
- INVESTCORP OFFICIALLY AWARDED THE BKY PROJECT
- INVESTCORP ANNOUNCES NATIONAL DAY HOLIDAY SCHEDULE – 02 SEPTEMBER 2026
- Groundbreaking Ceremony for Meiko Electronics Hai Duong Vietnam Factory and Warehouse Project
- Announcement of Holiday schedule for Hung Kings’ Commemoration Day and April 30 & May 1, 2026
- Seminar Celebrating International Women’s Day
- INVESTCORP Group’s Early Spring Pilgrimage for Good Fortune at Am Tien Temple – Nua Mountain, Thanh Hoa
COPYRIGHT © 2021 INVESTCORP. ALL RIGHT RESERVED