Update construction progress in June 2021 – Dong Nam Residential area infrastructure project in Dong Khe commune, Dong Son district, Thanh Hoa province
In June 2021, at the Dong Nam Residential area infrastructure project, INVESTCORP Land Thanh Hoa completed 80% of the road foundation and underground low-voltage electricity lines; completed the entire installation of light poles, 60% of pavements, 95% of green trees and 90% of clean water supply items.
It is expected that in July 2021, INVESTCORP Land Thanh Hoa will complete the road foundation and carry out asphalt concrete for all roads; complete pulling and spreading low-voltage cables and medium-voltage cables, install electrical cabinets and complete the foundation of 2 substations. The construction of planting green trees and paving sidewalks in the infrastructure area will also be carried out.



Other news
- INVESTCORP Group Commences Construction of Meiko Yen Quang Project
- Groundbreaking Ceremony for the Construction and Finishing of ACM Wastewater Treatment Plant
- INVESTCORP OFFICIALLY AWARDED THE BKY PROJECT
- INVESTCORP ANNOUNCES NATIONAL DAY HOLIDAY SCHEDULE – 02 SEPTEMBER 2026
- Groundbreaking Ceremony for Meiko Electronics Hai Duong Vietnam Factory and Warehouse Project
- Announcement of Holiday schedule for Hung Kings’ Commemoration Day and April 30 & May 1, 2026
- Seminar Celebrating International Women’s Day
- INVESTCORP Group’s Early Spring Pilgrimage for Good Fortune at Am Tien Temple – Nua Mountain, Thanh Hoa
COPYRIGHT © 2021 INVESTCORP. ALL RIGHT RESERVED