Update construction progress – Golden Land Project Pharmaceutical Factory in May 2019
In May 2019, INVESTCORP Myanmar continued implementing workshop and underground tank system. The PIT foundation system has been carried out 80% and will be completed in June 2019.
At the outdoor area, INVESTCORP Myanmar has basically completed the drainage system and 80% of the internal concrete road. It is expected that erection of the fence and installation of the main gate will be implemented and completed in June 2019.
Some auxiliary items such as manholes have been completed 60% and pump pits have been basically deployed etc.


Other news
- INVESTCORP Group Commences Construction of Meiko Yen Quang Project
- Groundbreaking Ceremony for the Construction and Finishing of ACM Wastewater Treatment Plant
- INVESTCORP OFFICIALLY AWARDED THE BKY PROJECT
- INVESTCORP ANNOUNCES NATIONAL DAY HOLIDAY SCHEDULE – 02 SEPTEMBER 2026
- Groundbreaking Ceremony for Meiko Electronics Hai Duong Vietnam Factory and Warehouse Project
- Announcement of Holiday schedule for Hung Kings’ Commemoration Day and April 30 & May 1, 2026
- Seminar Celebrating International Women’s Day
- INVESTCORP Group’s Early Spring Pilgrimage for Good Fortune at Am Tien Temple – Nua Mountain, Thanh Hoa
COPYRIGHT © 2021 INVESTCORP. ALL RIGHT RESERVED