Update construction progress – Golden Land Project Pharmaceutical Factory in June 2019
In June 2019, the workshop was finished brickwork and some basic finishing works. The pump room and the guardhouse have also been implemented brickwork.
At the outdoor area, INVESTCORP Myanmar has basically completed the internal concrete road and expect to complete it in July 2019. Items of fences, main gates etc. are continued to be executed.
The auxiliary items including pump pits, manholes and access pits will also be fully implemented in July 2019.


Other news
- INVESTCORP Group Commences Construction of Meiko Yen Quang Project
- Groundbreaking Ceremony for the Construction and Finishing of ACM Wastewater Treatment Plant
- INVESTCORP OFFICIALLY AWARDED THE BKY PROJECT
- INVESTCORP ANNOUNCES NATIONAL DAY HOLIDAY SCHEDULE – 02 SEPTEMBER 2026
- Groundbreaking Ceremony for Meiko Electronics Hai Duong Vietnam Factory and Warehouse Project
- Announcement of Holiday schedule for Hung Kings’ Commemoration Day and April 30 & May 1, 2026
- Seminar Celebrating International Women’s Day
- INVESTCORP Group’s Early Spring Pilgrimage for Good Fortune at Am Tien Temple – Nua Mountain, Thanh Hoa
COPYRIGHT © 2021 INVESTCORP. ALL RIGHT RESERVED