Construction progress updated in September 2022 – Sakata Inx Vietnam Factory Project - Bac Ninh Branch
On September 14, 2022, Investor Sakata and Main contractor Nishimatsu held the groundbreaking ceremony to officially started the construction work under the contract.
In September 2022, for the factory, INVESTCORP 15 has carried out the excavation of the factory foundation and pouring the foundation concrete. At the same time, INVESTCORP 15 is implementing the construction of rainwater drainage sewers, reaching about 50% of the volume.
It is expected that in October 2022, INVESTCORP 15 will complete the construction of the concrete for the factory foundation and bracing to hand over the site to erect the reinforced concrete structure.

Other news
- INVESTCORP Group Commences Construction of Meiko Yen Quang Project
- Groundbreaking Ceremony for the Construction and Finishing of ACM Wastewater Treatment Plant
- INVESTCORP OFFICIALLY AWARDED THE BKY PROJECT
- INVESTCORP ANNOUNCES NATIONAL DAY HOLIDAY SCHEDULE – 02 SEPTEMBER 2026
- Groundbreaking Ceremony for Meiko Electronics Hai Duong Vietnam Factory and Warehouse Project
- Announcement of Holiday schedule for Hung Kings’ Commemoration Day and April 30 & May 1, 2026
- Seminar Celebrating International Women’s Day
- INVESTCORP Group’s Early Spring Pilgrimage for Good Fortune at Am Tien Temple – Nua Mountain, Thanh Hoa
COPYRIGHT © 2021 INVESTCORP. ALL RIGHT RESERVED