Construction progress updated in September 2022 – Expansion project of Meiko Quang Minh manufacturing and assembling electronic components factory - Phase 1
At the end of September 2022, INVESTCORP Dong Minh has completed the construction of items of the PCB building such as construction of the 2nd floor columns, the 3rd floor beams, the 3rd floor columns, the roof floor beams, the attic beams, and dismantling formwork of beams and slabs.
Regarding the parking house, INVESTCORP Dong Minh has completed the construction of the beams and slabs on the 2nd floor, the columns on the 2nd floor, the roof beams, and the attic columns.
For the ancillary items such as the electric house, cooling house & compressor house, and boiler house, INVESTCORP Dong Minh has 100% completed staircases and walls. Wall plastering is constructed in parallel.
As planned in October 2022, INVESTCORP Dong Minh will continue to implement the construction of the PCB house, underground water tank, parking house and other ancillary items according to the contract plan.

- INVESTCORP Group Commences Construction of Meiko Yen Quang Project
- Groundbreaking Ceremony for the Construction and Finishing of ACM Wastewater Treatment Plant
- INVESTCORP OFFICIALLY AWARDED THE BKY PROJECT
- INVESTCORP ANNOUNCES NATIONAL DAY HOLIDAY SCHEDULE – 02 SEPTEMBER 2026
- Groundbreaking Ceremony for Meiko Electronics Hai Duong Vietnam Factory and Warehouse Project
- Announcement of Holiday schedule for Hung Kings’ Commemoration Day and April 30 & May 1, 2026
- Seminar Celebrating International Women’s Day
- INVESTCORP Group’s Early Spring Pilgrimage for Good Fortune at Am Tien Temple – Nua Mountain, Thanh Hoa