Construction progress updated in September 2021 – Project of Repairing damage of roadbed, road surface and drainage system section Km3+00 -:- Km10+500, National way 47B, Thanh Hoa province
The project of repairing damaged roadbed, road surface and surface water drainage system of National way 47B, Thanh Hoa province is invested by the Transportation Department of Thanh Hoa province with a total length of nearly 2.5 km, including the following items: repairing road surface, repairing and installing load-bearing drainage system, installing signal system, pickets, painting road markings...
In September 2021, INVESTCORP Land Thanh Hoa Company has constructed 85% of the drainage system and 77% of asphalt concrete work.
According to the plan, the entire remaining work volume includes asphalt concrete work, construction of ditches pending site clearance and signaling system (painting road markings, installing signs, pickets...) will be completed construction in October 2021.


- INVESTCORP Group Commences Construction of Meiko Yen Quang Project
- Groundbreaking Ceremony for the Construction and Finishing of ACM Wastewater Treatment Plant
- INVESTCORP OFFICIALLY AWARDED THE BKY PROJECT
- INVESTCORP ANNOUNCES NATIONAL DAY HOLIDAY SCHEDULE – 02 SEPTEMBER 2026
- Groundbreaking Ceremony for Meiko Electronics Hai Duong Vietnam Factory and Warehouse Project
- Announcement of Holiday schedule for Hung Kings’ Commemoration Day and April 30 & May 1, 2026
- Seminar Celebrating International Women’s Day
- INVESTCORP Group’s Early Spring Pilgrimage for Good Fortune at Am Tien Temple – Nua Mountain, Thanh Hoa