Construction progress updated in October 2022 – Expansion project of Meiko Quang Minh manufacturing and assembling electronic components factory - Phase 1
At the end of October 2022, INVESTCORP Dong Minh has completed the construction of items in the PCB house, including construction of lift table foundation, reinforced concrete construction, stair formwork; the construction of corrugated iron walls and installation of corrugated iron wall doors is also being implemented in parallel.
For the Underground water tank – Parking house, INVESTCORP Dong Minh has completed the construction of sloping floor beam to the parking house, construction of stairs, and dismantling formwork of floor beams. At the Power House, Cooling House and Air Compressor, INVESTCORP Dong Minh has completed about 90% of the plastering and is implementing waterproofing and heat-proofing for the roof. In addition, INVESTCORP Dong Minh has also completed the construction of stairs, construction and dismantling of floor beam formwork at the Boiler house.
It is expected that by the end of November 2022, INVESTCORP Dong Minh will basically complete the items of PCB house, Underground water tank, Parking house, and Boiler house. Other works continue to be implemented according to the contract plan.

- INVESTCORP Group Commences Construction of Meiko Yen Quang Project
- Groundbreaking Ceremony for the Construction and Finishing of ACM Wastewater Treatment Plant
- INVESTCORP OFFICIALLY AWARDED THE BKY PROJECT
- INVESTCORP ANNOUNCES NATIONAL DAY HOLIDAY SCHEDULE – 02 SEPTEMBER 2026
- Groundbreaking Ceremony for Meiko Electronics Hai Duong Vietnam Factory and Warehouse Project
- Announcement of Holiday schedule for Hung Kings’ Commemoration Day and April 30 & May 1, 2026
- Seminar Celebrating International Women’s Day
- INVESTCORP Group’s Early Spring Pilgrimage for Good Fortune at Am Tien Temple – Nua Mountain, Thanh Hoa