Construction progress updated in May 2023 - Renovation and upgrading project of provincial road 506B, section from Tho Lap commune to Xuan Tin commune, Tho Xuan district
In May 2023, INVESTCORP Land Thanh Hoa excavated and transported weathered soil with 43% of the work volume; transported and embanked the K95 reached 18% of the volume. For the drainage system, the Company is implementing the construction of horizontal culvert steel.
As planned in June 2023, INVESTCORP Land Thanh Hoa will focus on carrying out the construction of the road surface, speeding up the excavation of weathering soil, embankment of K95 for the whole road, and at the same time implementing the construction of the drainage system.

Other news
- INVESTCORP Group Commences Construction of Meiko Yen Quang Project
- Groundbreaking Ceremony for the Construction and Finishing of ACM Wastewater Treatment Plant
- INVESTCORP OFFICIALLY AWARDED THE BKY PROJECT
- INVESTCORP ANNOUNCES NATIONAL DAY HOLIDAY SCHEDULE – 02 SEPTEMBER 2026
- Groundbreaking Ceremony for Meiko Electronics Hai Duong Vietnam Factory and Warehouse Project
- Announcement of Holiday schedule for Hung Kings’ Commemoration Day and April 30 & May 1, 2026
- Seminar Celebrating International Women’s Day
- INVESTCORP Group’s Early Spring Pilgrimage for Good Fortune at Am Tien Temple – Nua Mountain, Thanh Hoa
COPYRIGHT © 2021 INVESTCORP. ALL RIGHT RESERVED