Construction progress updated in May 2023 – Additional tender package for construction of “Rooftop solar power system” under ‘‘Wearing apparel manufacturing factory project of Maple Company in Hai Phong’’
At the end of May 2023, INVESTCORP 10 completed pouring the roof pillars of Factories 1, 2, 3, and 4 and the roofs of Offices 1 and 2. At the same time, the Company is also processing battery racks and has completed the installation of Factories 1 and 2’s panel racks and the construction of control rooms of Factories 1 and 2.
As planned in June 2023, INVESTCORP 10 will carry out the installation of panel racks and control rooms of Factories 3 and 4.


Other news
- INVESTCORP Group Commences Construction of Meiko Yen Quang Project
- Groundbreaking Ceremony for the Construction and Finishing of ACM Wastewater Treatment Plant
- INVESTCORP OFFICIALLY AWARDED THE BKY PROJECT
- INVESTCORP ANNOUNCES NATIONAL DAY HOLIDAY SCHEDULE – 02 SEPTEMBER 2026
- Groundbreaking Ceremony for Meiko Electronics Hai Duong Vietnam Factory and Warehouse Project
- Announcement of Holiday schedule for Hung Kings’ Commemoration Day and April 30 & May 1, 2026
- Seminar Celebrating International Women’s Day
- INVESTCORP Group’s Early Spring Pilgrimage for Good Fortune at Am Tien Temple – Nua Mountain, Thanh Hoa
COPYRIGHT © 2021 INVESTCORP. ALL RIGHT RESERVED