Construction progress updated in March 2023 – Sao Mai Resort Project, Tho Lam Commune – Tho Xuan District – Thanh Hoa Province
In March 2023, INVESTCORP 6 continued to construct items, including reception house, Rubby Four Seasons villa area, Bungalow under the lake and other ancillary items.
For the reception house, INVESTCORP 6 has completed the construction of the concrete structure; for the Rubby Four Seasons Villa and Bungalow under the lake have been completed by INVESTCORP 6 inside and outside for handover to the Investor in April 2023.
In addition, in March 2023, INVESTCORP 6 also completed 100% of other ancillary items such as generator room 1 and 2, tennis court and laundry house. It is expected that in April 2023, the Company will complete the remaining items to hand over to the Investor.


Other news
- INVESTCORP Group Commences Construction of Meiko Yen Quang Project
- Groundbreaking Ceremony for the Construction and Finishing of ACM Wastewater Treatment Plant
- INVESTCORP OFFICIALLY AWARDED THE BKY PROJECT
- INVESTCORP ANNOUNCES NATIONAL DAY HOLIDAY SCHEDULE – 02 SEPTEMBER 2026
- Groundbreaking Ceremony for Meiko Electronics Hai Duong Vietnam Factory and Warehouse Project
- Announcement of Holiday schedule for Hung Kings’ Commemoration Day and April 30 & May 1, 2026
- Seminar Celebrating International Women’s Day
- INVESTCORP Group’s Early Spring Pilgrimage for Good Fortune at Am Tien Temple – Nua Mountain, Thanh Hoa
COPYRIGHT © 2021 INVESTCORP. ALL RIGHT RESERVED