Construction progress updated in March 2022 – Manufacturing eco-friendly decor product project
In March 2022, INVESTCORP 15 has completed items, including: painting the internal and external walls in the factory, installing iron doors, quick rolling doors and ditch cover system. The office has been completed the tiling of the toilet area, stairs, aluminum and glass facades and aluminum facade panels for the office by INVESTCORP 15. The ceiling and drywall work are also being urgently constructed.
It is expected that in April 2022, INVESTCORP 15 will complete the construction of the office, including the construction of drywall ceilings, aluminum ceilings, sound-absorbing ceiling panels, glass partitions, office wooden doors, wooden furniture and other finishes.


Other news
- INVESTCORP Group Commences Construction of Meiko Yen Quang Project
- Groundbreaking Ceremony for the Construction and Finishing of ACM Wastewater Treatment Plant
- INVESTCORP OFFICIALLY AWARDED THE BKY PROJECT
- INVESTCORP ANNOUNCES NATIONAL DAY HOLIDAY SCHEDULE – 02 SEPTEMBER 2026
- Groundbreaking Ceremony for Meiko Electronics Hai Duong Vietnam Factory and Warehouse Project
- Announcement of Holiday schedule for Hung Kings’ Commemoration Day and April 30 & May 1, 2026
- Seminar Celebrating International Women’s Day
- INVESTCORP Group’s Early Spring Pilgrimage for Good Fortune at Am Tien Temple – Nua Mountain, Thanh Hoa
COPYRIGHT © 2021 INVESTCORP. ALL RIGHT RESERVED