Construction progress updated in June 2023 - Renovation and upgrading project of provincial road 506B, section from Tho Lap commune to Xuan Tin commune, Tho Xuan district
In June 2023, INVESTCORP Land Thanh Hoa focused on implementing the construction of road surfaces and drainage systems.
For road surface items, the Company focused on excavating and transporting weathered soil, reaching 63% of the volume; the K95's transportation and embankment work reached 51% of the volume. At the same time, the drainage system and construction of horizontal culvert steel were also implemented in parallel by INVESTCORP Land Thanh Hoa.
As planned in July 2023, the Company will continue to implement the construction of the road surface and drainage system.

Other news
- INVESTCORP Group Commences Construction of Meiko Yen Quang Project
- Groundbreaking Ceremony for the Construction and Finishing of ACM Wastewater Treatment Plant
- INVESTCORP OFFICIALLY AWARDED THE BKY PROJECT
- INVESTCORP ANNOUNCES NATIONAL DAY HOLIDAY SCHEDULE – 02 SEPTEMBER 2026
- Groundbreaking Ceremony for Meiko Electronics Hai Duong Vietnam Factory and Warehouse Project
- Announcement of Holiday schedule for Hung Kings’ Commemoration Day and April 30 & May 1, 2026
- Seminar Celebrating International Women’s Day
- INVESTCORP Group’s Early Spring Pilgrimage for Good Fortune at Am Tien Temple – Nua Mountain, Thanh Hoa
COPYRIGHT © 2021 INVESTCORP. ALL RIGHT RESERVED