Construction progress updated in June 2022 – Technical infrastructure project of residential area in Quang Dong commune, Thanh Hoa city, Thanh Hoa province
In June 2022, INVESTCORP Land Thanh Hoa Co., Ltd. has implemented the works including construction of K98 embankment reached 83%; installation of surface water drainage system reached 38% of the volume. The roads that have been constructed include: road 1, road 2, road 3, road 5, and road 6. Casting concrete for pavement structures, installing and building manholes and drainage pits continue to be constructed and reached 70% by volume.
It is expected that in July 2022, INVESTCORP Land Thanh Hoa will focus on completing the construction of K95 and K98 embankment, construction of sidewalks and installation of rainwater drainage systems, processing and pouring concrete pavement components.

Other news
- INVESTCORP Group Commences Construction of Meiko Yen Quang Project
- Groundbreaking Ceremony for the Construction and Finishing of ACM Wastewater Treatment Plant
- INVESTCORP OFFICIALLY AWARDED THE BKY PROJECT
- INVESTCORP ANNOUNCES NATIONAL DAY HOLIDAY SCHEDULE – 02 SEPTEMBER 2026
- Groundbreaking Ceremony for Meiko Electronics Hai Duong Vietnam Factory and Warehouse Project
- Announcement of Holiday schedule for Hung Kings’ Commemoration Day and April 30 & May 1, 2026
- Seminar Celebrating International Women’s Day
- INVESTCORP Group’s Early Spring Pilgrimage for Good Fortune at Am Tien Temple – Nua Mountain, Thanh Hoa
COPYRIGHT © 2021 INVESTCORP. ALL RIGHT RESERVED