Construction progress updated in June 2022 - New Factory Construction Project of AIR WATER Vietnam Co., Ltd in Ha Nam
In June 2022, INVESTCORP 15 has completed items including construction of foundation and walls. In the office area, the finishing works of plastering and toilet tiling are being implemented.
Work items related to the construction of the new factory, including plastering and tiling, will be focused on constructing and completing by INVESTCORP 15 in July 2022.


Other news
- INVESTCORP Group Commences Construction of Meiko Yen Quang Project
- Groundbreaking Ceremony for the Construction and Finishing of ACM Wastewater Treatment Plant
- INVESTCORP OFFICIALLY AWARDED THE BKY PROJECT
- INVESTCORP ANNOUNCES NATIONAL DAY HOLIDAY SCHEDULE – 02 SEPTEMBER 2026
- Groundbreaking Ceremony for Meiko Electronics Hai Duong Vietnam Factory and Warehouse Project
- Announcement of Holiday schedule for Hung Kings’ Commemoration Day and April 30 & May 1, 2026
- Seminar Celebrating International Women’s Day
- INVESTCORP Group’s Early Spring Pilgrimage for Good Fortune at Am Tien Temple – Nua Mountain, Thanh Hoa
COPYRIGHT © 2021 INVESTCORP. ALL RIGHT RESERVED