Construction progress updated in January 2023 – Typical Residential Area Infrastructure Project in Hoang Hoc Village, Dong Hoang Commune, Dong Son District, Thanh Hoa Province
By the end of January 2023, INVESTCORP Land Thanh Hoa has basically completed the construction of drainage ditches and campus items together with the construction of watering asphalt to the road surface reaches 60% of the volume. Total construction volume is estimated at 97% of contract volume.
It is planned that in February 2023, INVESTCORP Land Thanh Hoa will carry out pouring asphalt on the remaining roads of the project, completing the construction of pavement tiles, completing the installation of the water and power supply system, and construction of green campus.


Other news
- INVESTCORP Group Commences Construction of Meiko Yen Quang Project
- Groundbreaking Ceremony for the Construction and Finishing of ACM Wastewater Treatment Plant
- INVESTCORP OFFICIALLY AWARDED THE BKY PROJECT
- INVESTCORP ANNOUNCES NATIONAL DAY HOLIDAY SCHEDULE – 02 SEPTEMBER 2026
- Groundbreaking Ceremony for Meiko Electronics Hai Duong Vietnam Factory and Warehouse Project
- Announcement of Holiday schedule for Hung Kings’ Commemoration Day and April 30 & May 1, 2026
- Seminar Celebrating International Women’s Day
- INVESTCORP Group’s Early Spring Pilgrimage for Good Fortune at Am Tien Temple – Nua Mountain, Thanh Hoa
COPYRIGHT © 2021 INVESTCORP. ALL RIGHT RESERVED