Construction progress updated in February 2023 - Vina Ito Factory Project Phase 2
In February 2023, INVESTCORP 15 has completed building and plastering the factory walls, constructing layer 1 of the internal road and rainwater drainage system. Along with that, the construction of the garbage house walls and the installation of V steels for manhole covers are also being implemented by INVESTCORP 15.
It is expected that in March 2023, after the Investor confirms the factory floor concrete plan, INVESTCORP 15 will complete constructing the remaining concrete of the factory floor. Besides, the installation of curbs, internal roads, tiling toilets and pouring concrete of manhole necks will also complete 100% of the work volume.
In addition, the garbage house item will also be urgently constructed by INVESTCORP 15 to hand over to the Investor in mid-March 2023. At the same time, the internal asphalt spread will be carried out according to the Main contractor's plan, and the remaining cleaning and repair work will also be performed by INVESTCORP 15 in parallel.

- INVESTCORP Group Commences Construction of Meiko Yen Quang Project
- Groundbreaking Ceremony for the Construction and Finishing of ACM Wastewater Treatment Plant
- INVESTCORP OFFICIALLY AWARDED THE BKY PROJECT
- INVESTCORP ANNOUNCES NATIONAL DAY HOLIDAY SCHEDULE – 02 SEPTEMBER 2026
- Groundbreaking Ceremony for Meiko Electronics Hai Duong Vietnam Factory and Warehouse Project
- Announcement of Holiday schedule for Hung Kings’ Commemoration Day and April 30 & May 1, 2026
- Seminar Celebrating International Women’s Day
- INVESTCORP Group’s Early Spring Pilgrimage for Good Fortune at Am Tien Temple – Nua Mountain, Thanh Hoa