Construction progress updated in December 2021 – Typical Residential Area Infrastructure Project in Hoang Hoc Village, Dong Hoang Commune, Dong Son District, Thanh Hoa Province
At the end of December 2021, INVESTCORP Land Thanh Hoa Company Limited has completed 90% of K95 embankment, 80% of K98 embankment, 60% of grade 2 crushed stone road construction, 40% of curb installation, 45% of surface water and wastewater drainage systems. Besides, the volume of trees on the sidewalks has also been planted by 50%.
It is expected that in January 2022, INVESTCORP Land Thanh Hoa will continue to construct K95, K98 embankment for the foundation of roads and the ditch and sewer system. At the same time, the construction and installation of low-voltage power systems, crushed stone for roads and installation of sidewalk curbs will also be carried out.


Other news
- INVESTCORP Group Commences Construction of Meiko Yen Quang Project
- Groundbreaking Ceremony for the Construction and Finishing of ACM Wastewater Treatment Plant
- INVESTCORP OFFICIALLY AWARDED THE BKY PROJECT
- INVESTCORP ANNOUNCES NATIONAL DAY HOLIDAY SCHEDULE – 02 SEPTEMBER 2026
- Groundbreaking Ceremony for Meiko Electronics Hai Duong Vietnam Factory and Warehouse Project
- Announcement of Holiday schedule for Hung Kings’ Commemoration Day and April 30 & May 1, 2026
- Seminar Celebrating International Women’s Day
- INVESTCORP Group’s Early Spring Pilgrimage for Good Fortune at Am Tien Temple – Nua Mountain, Thanh Hoa
COPYRIGHT © 2021 INVESTCORP. ALL RIGHT RESERVED