Construction progress updated in August 2023 - TOYO INK COMPOUNDS Vietnam Factory Project Phase 3
At the end of August 2023, INVESTCORP 10 basically completed pouring heat-resistant concrete for the roof, painting and removing the scaffolding outside the house; complete indoor wall and ceiling beams for the factory.
In the warehouse area, INVESTCORP 10 completed the construction of plastering, painting, and connections to the current factory. In addition, the Company also completed the installation of the rainwater drainage system.
It is expected that in September 2023, INVESTCORP 10 will complete all remaining items, and will conduct acceptance with the Main Contractor and Investor.


Other news
- INVESTCORP Group Commences Construction of Meiko Yen Quang Project
- Groundbreaking Ceremony for the Construction and Finishing of ACM Wastewater Treatment Plant
- INVESTCORP OFFICIALLY AWARDED THE BKY PROJECT
- INVESTCORP ANNOUNCES NATIONAL DAY HOLIDAY SCHEDULE – 02 SEPTEMBER 2026
- Groundbreaking Ceremony for Meiko Electronics Hai Duong Vietnam Factory and Warehouse Project
- Announcement of Holiday schedule for Hung Kings’ Commemoration Day and April 30 & May 1, 2026
- Seminar Celebrating International Women’s Day
- INVESTCORP Group’s Early Spring Pilgrimage for Good Fortune at Am Tien Temple – Nua Mountain, Thanh Hoa
COPYRIGHT © 2021 INVESTCORP. ALL RIGHT RESERVED